 Canyon trails Recreation Center Photo   May 4, 2012
The Recreation Area is Now Open and residents are enjoying the har-tru tennis courts, full-basketball court, party pavilion and all of the open play space. The Grand Opening Party for the Rec Site was a huge success! Soon construction will be underway for the Clubhouse.
 Canyon Trails Aerial Photo  Canyon Trails Aerial Photo
    April 4, 2012
Residents are excited for the grand opening of the first phase of the rec site, which includes the tennis courts, full basketball court, party pavilion and more


    October 27, 2011
Earthwork is completed in Parcel A-4 and pipework is starting.
Phase I of the recreation area will be opening in February of 2012 and will feature Basketball, Tennis, Tot-lot, Open Play and a Party Pavilion.
    September 28, 2011
Eight gorgeous lakes make the views around the community amazing. With the release of our two new parcels, construction is underway and there is a lot of work going on. Residents are excited for the progress on the clubhouse. Be on the lookout for the new tennis courts and party pavilion being built.
    August 26, 2011
More and more homeowners are moving in. We're clearing the land for new sections of the community.
    July 25, 2011
Earthwork is underway in Parcel A.
    July 5, 2011
Development is starting on Plat Four, which is the last Parcel in Phase I.


April 22, 2011
Eight lakes are completed. The entry and spine road are paved. Models, guardhouse, entry and the Turnpike buffer are 100% complete. Development is 100% complete in Parcels A1, A2 and A3 and in Parcel B.


March 23, 2011
Canyon Trails has welcomed the community's first residents and further closings are underway at Canyon Trails.


February 24, 2011
Eight lakes are completed. The entry and spine road are paved. Models, guardhouse, entry and the Turnpike buffer are 100% complete. Development is 100% complete in Parcels A1, A2 and A3 and in Parcel B.
February 12, 2011
Eight new decorated models are now open for touring. Guests enjoy a multi-sport court in the middle of model row.

MODEL GRAND OPENING
PHOTO GALLERY



January 28, 2011
Eight lakes are completed. The entry and spine road are paved. Models, guardhouse and entry 90% complete.The Turnpike buffer is 90% complete. Development is 100% complete in Parcels A1 and A2, 90% complete in Parcels A3 and is under construction in Parcel B.


December 24, 2010
Eight lakes are completed. The entry and spine road are paved. Models, guardhouse and entry are under construction. Acme Dairy Road buffer is 100% complete and the Turnpike buffer is 75% complete. Development is 100% complete in Parcels A1 and A2, 85% complete in Parcels A3 and is under construction in Parcel B


December 07, 2010
Eight new, decorated models for Canyon Trails are well underway and will be all decked out just in time for the Grand Opening celebration coming early in 2011. Just for fun, GL Homes is even creating an outdoor sports court in the Model Center.


November 24, 2010
Eight lakes are complete, the entry & spine roads are paved and the entry, guardhouse and models are all under construction. Development is 100% complete in Parcels B, A-1 and A-2 and 85% in Parcel A-3. The Acme Dairy Road Buffer is 100% complete and the Turnpike Buffer is 75% complete.


November 09, 2010
Lettering has been installed at the Canyon Trails entry monument and the roof is going up on the gatehouse!


October 26, 2010
The soon-to-be spectacular entrance for Canyon Trails is in progress! Cultured stone is being applied to the entry monument and the rock waterfalls are under construction. Watch for the granite sign face and Canyon Trails lettering coming soon.

An elevated entryway leads to the gatehouse. The "shell" is being created and the water features are under on-going construction.


October 26, 2010
The Canyon Trails Welcome Center will feature eight gorgeous decorated models and a sales center. There are plans for one model to feature Smart Home Technology.

As seen in these two views, model construction is well underway. A Model Grand Opening is planned for early in 2011.


September 30, 2010
Lakes # 1, 2, 3, 5, 6 & 7 are 90% complete and Lake # 4 & 8 are 60% complete.
Entry Road is 100% complete and the Guardhouse and Entry Features are both under construction. Earthwork and Underground Utilities are 100% complete on the Spine Road North as well as Pod B and parts of Pod A



August 27, 2010
Lakes # 1, 2, 3, 5, 6 & 7 are 90% excavated and Lake # 4 & 8 are 50% complete. Earthwork and Underground Utilities are completed on the entry and spine roads. Guardhouse and entry features are under construction.