Windows and exterior doors are now being installed

Saturday, July 1, 2017

Stonecreek Clubhouse Construction
Exciting new developments are happening at StoneCreek. Two new models, the Rosé and the Bellagio, are currently under construction and work has begun on new houses in the last parcel. At the clubhouse, the spa, main pool, and lap pool shell have been completed and are ready for filling. The tennis courts and pickleball courts have been scraped and fill dirt has been delivered. The windows and exterior doors have been installed and stucco is scheduled in the upcoming weeks.
×